The project consisted of the construction of 970 lf of 12 inch diameter sanitary sewer pipe, four new sanitary sewer manholes, five sewer laterals and the modification of an existing sewer manhole. In addition, a portion of the sewer was removed and redirected to lower the peak flow on an existing sewer line that was operating beyond its designed capacity.
Acme Underground was able to help value engineer a sewer by-pass plan that did not utilize by-pass pumps saving the City of Henderson a significant amount of cost on the contract.
Acme Underground completed the project ahead of schedule and under budget.